Bus Stop Improvements

Stockport - Urmston QBC
Trafford MBC

Value: £120,000

Duration: March - May 2008

Footway improvements to 22 bus stop locations including raising of kerbs, paving, bus stop poles and ducting.

Broad Road Bus Stops, Sale
Trafford MBC

Value: £23,000

Duration: November – December 2007

Civil Engineering works to new double bus stop including installation of Kassel kerbs, paving, ducting and surfacing.

Edge Lane, Stretford
Trafford MBC/GMPTE

Value: £36,000

Duration: February - March 2007

Improvements to 10 bus stops in line with GMPTE quality bus corridor policy.